St James School, Ashford   |   Procurement process

Project Details
Client:
Contractor:
Local Authority:
Summary

The client required that the procurement process for the development of the new school buildings, a project that might normally take at least 24 months from inception to occupation, to be accelerated to a 13-month programme to allow the school to open in September 2010. As the school could only move during the summer holiday period, missing this date would incur significant loss of income (loss ...